Day 540: Fittings in Classrooms and Bathrooms In Progress

Interior work at the new campus site has started to move quickly especially in the classrooms and bathrooms. After bathroom floor tiling was completed, partition doors (orange and yellow) were installed in the different student and adult bathrooms. Sanitary ware including toilets and sinks were also fitted in the bathrooms.

Read more

Day 526: Architectural Work Continues at Rapid Pace

Work continues at a rapid pace at the new campus with the majority of construction milestones on schedule if not ahead of schedule. Flooring is complete on the second and third floor of the buildings. Window frames and glass are currently being installed in classrooms and the front building. The

Read more

Day 507: Teachers Visit New Campus

On the last day of August In-Service, the academic staff of Magic Years ventured outside the school premises to visit their future home and the site of the new Magic Years campus! In preparation for the move to the new campus (only a few short months away), the staff of

Read more

Day 490: Significant Progress Over the Summer

The summer months are nearing its end and during this time we have seen significant progress at the new campus. The masonry work is 100% complete along with the plastering of the interior walls and the first layer of paint. Much of the flooring is finished including in the large

Read more

Day 422: Masonry Work 90% Complete

The masonry work for the new campus is now 90% complete. Walking into the buildings with the walls newly constructed gives a sense of the spacious classrooms and learning spaces for the students. The construction workers have also begun the plastering work for the classroom walls and the ceiling slabs.

Read more

Day 396: Masonry Work in Classrooms

After a short break during the Songkran holidays, the masonry work at the new campus has resumed. The masonry work is now being carried out on all three floors of the buildings, including the classrooms, bathrooms, parent room, infirmary room, music room and science lab. A large crane was brought

Read more

Day 373: Masonry Work Begins

The structural work of the buildings at the new campus site is now days away from completion. Workers are making final repairs to the structure in order to prepare for the next phase of construction: the architectural work. The structure of the school’s amphitheatre is close to completion. Steel tie

Read more

Day 341: Roof Metal Sheet Installation Nearing Completion

On Day 341, the roof structure is looking more complete as the light-green colored metal sheet installation is nearing completion. Meanwhile, heavy machinery has also been brought in to fill and level the land of the L-shaped playground, the centerpiece of the new campus. Work has also been progressing in

Read more

Day 317: Steel Roof Structure Work Begins

The west wing of the new campus has made several advances as workers at the site began to lay steel form work underneath the roof slab to support the roof structure. Concrete was then poured for the roof slabs of the west wing. At the same time, the roof slabs

Read more

Day 299: Roof Structure Advancing

Over the past month, steel tie work, steel form work and concrete pouring were completed for the third floor columns in the west wing. At the same time, steel tie work for the roof slabs in the northeast and southeast wing had begun. This was followed by concrete pouring for

Read more