Day 192: Second floor continued progress
Despite the heavy rains, there is significant progress on the second floor of the school building. Pre-cast concrete planks have been positioned on the floor of the vast west wing of the campus. In the north wing, steel tie work and concrete pouring is already underway for the second floor