After the pre-cast concrete planks were installed on the second floor of the north wing and wire mesh was put into place, concrete trucks were brought to the site to begin pouring concrete for the first topping layer of the second floor. A large crane was utilized to lift heavy drums of concrete to the second floor level. At the same time, work continued on the ground floor to create wooden form work for the staircase to second floor. At the west wing of the school campus, steel tie work and steel form work is currently in progress to prepare the second floor beams.
Day 173: Second Floor Concrete Topping