It’s an exciting time at the new campus as work for the third (and final) floor of the buildings is in progress. After concrete pouring was completed for all columns on the second floor, the steel tie work and form work for the third floor concrete slabs got underway. This was followed by concrete pouring at the Northeast wing after which the side steel form work was removed from the third floor beams. Steel support structures were then installed in between the concrete beams to support the upcoming plank laying for the third floor.
Day 219: Third Floor Work In Progress