Day 270: Signature Tree Installed
The new campus’ signature tree which is situated in the school’s main playground has now been installed. After visiting Nakhon Nayok province and viewing several potential signature trees, the school’s owners decide to select a “cork tree” to be the main feature of the playground. The tree was transported from
Day 268: Structural Work for Roof Beams Begins
Structural work for the main buildings at the new campus is entering its final phase as steel support, wood form work and steel tie work is being installed for the roof’s beams for the southeast and northeast wing. Steel form work has also continued for the lift shaft in the
Day 251: Third Floor Concrete Topping Complete
Work has been progressing on several different fronts of the new school campus – especially on the third floor of the main buildings. The steel form work for the third floor columns for the northeast wing and the east wing is near completion. Steel tie work for the elevator shaft
Day 236: Third Floor Structure Advancing
Wooden form work and steel tie work is being carried out for the third floor concrete beams in the large expanse of the west wing. Steel tie work is also under way for the staircase from the second floor to the third floor at the southeast wings. The concrete floor
Day 219: Third Floor Work In Progress
It’s an exciting time at the new campus as work for the third (and final) floor of the buildings is in progress. After concrete pouring was completed for all columns on the second floor, the steel tie work and form work for the third floor concrete slabs got underway. This