Day 540: Fittings in Classrooms and Bathrooms In Progress

Interior work at the new campus site has started to move quickly especially in the classrooms and bathrooms. After bathroom floor tiling was completed, partition doors (orange and yellow) were installed in the different student and adult bathrooms. Sanitary ware including toilets and sinks were also fitted in the bathrooms.

Day 526: Architectural Work Continues at Rapid Pace

Work continues at a rapid pace at the new campus with the majority of construction milestones on schedule if not ahead of schedule. Flooring is complete on the second and third floor of the buildings. Window frames and glass are currently being installed in classrooms and the front building. The

Day 507: Teachers Visit New Campus

On the last day of August In-Service, the academic staff of Magic Years ventured outside the school premises to visit their future home and the site of the new Magic Years campus! In preparation for the move to the new campus (only a few short months away), the staff of

Day 490: Significant Progress Over the Summer

The summer months are nearing its end and during this time we have seen significant progress at the new campus. The masonry work is 100% complete along with the plastering of the interior walls and the first layer of paint. Much of the flooring is finished including in the large

Day 422: Masonry Work 90% Complete

The masonry work for the new campus is now 90% complete. Walking into the buildings with the walls newly constructed gives a sense of the spacious classrooms and learning spaces for the students. The construction workers have also begun the plastering work for the classroom walls and the ceiling slabs.