Day 589: Final Stages of Architectural Construction

With just 6 weeks to go before the start of our move to the new campus, the architectural construction is in its final stages! The fence around the swimming pool is nearing completion. The hardwood rail has been installed along the fence of the swimming pool on one side and a protective metal louvre is being installed on the other side. The light fixtures, air-conditioners and paint finish is completed in the gym room and now the ground is being prepared for the multi-purpose flooring. The hardwood rails in the steel bridge, amphitheatre and signature tree area are now complete with a paint finish. All the wooden doors throughout the campus have also been installed with a paint finish. The staircase banisters and railings have also received a final sanding and paint finish.